Business Broadband Installation Lead Times and How to Plan Around Them

New sites get caught out by connectivity lead times more than any other utility. Here are realistic timelines.

8 July 2026 5 min read

Typical timelines

Standard FTTC or FTTP where infrastructure already exists is usually two to four weeks. A leased line requiring civil works can take 60 to 120 working days. Those are very different planning horizons.

Order at heads of terms, not at fit-out

The single most effective step is ordering connectivity as soon as the lease is agreed, not when the builders leave. It is the longest lead item in most fit-outs and the one most often started last.

Bridge the gap

A 4G/5G router keeps you trading while a permanent circuit is built. Budget for it upfront rather than scrambling in week one of trading.

Want this reviewed for your business?

Send us a recent bill and a consultant from our Cardiff office will tell you, honestly, whether you are paying more than you need to.

Find out what your business should be paying

Serving businesses across the UK from our Cardiff office.